Multifamily construction averaged 18.9 months from permit to completion in 2025, improving from 2024 but remaining above past norms.
Multifamily construction averaged 18.9 months from permit to completion in 2025, improving from 2024 but remaining above past norms.
  • Multifamily buildings averaged 18.9 months from authorization to completion in 2025, 0.7 months faster than in 2024.
  • The timeline remained 3.5 months longer than 2009 and nearly seven months above the 2013 period low.
  • The Northeast had the longest average permit-to-completion timeline at 21.9 months, while the Midwest was shortest at 16.6 months.
Key Takeaways

Eye on Housing reports that multifamily construction timelines improved modestly in 2025. Census Bureau Survey of Construction data show an average 18.9 months from permit authorization to completion, down about 0.7 months from 2024 despite the industry’s continued shortage of skilled labor.

Longer Than Historical Norms

The 2025 improvement did not reverse the longer-term increase in construction duration. Permit-to-completion time remained 3.5 months above the 15.4-month average recorded in 2009. It was also almost seven months longer than the 12-month period low in 2013. Most of the increase occurred during the construction phase. Average start-to-completion time rose from 13.4 months in 2009 to 16.5 months in 2025.

Multifamily permit-to-completion time fell to 18.9 months in 2025, while start-to-completion eased to 16.5 months.

The source attributes part of that increase to a growing share of larger multifamily properties, which generally take longer to deliver.

The Details

Project size remains a major differentiator. Buildings with 20 or more units took 21.7 months from authorization to completion in 2025. That was slightly faster than 22.1 months in 2024 but far above 16.2 months in 2015. Two-to-four-unit buildings finished fastest at 14.9 months, compared with 15.3 months in 2024 and 12 months in 2015.

Multifamily construction times in 2025 ranged from 14.9 months for 2–4 units to 21.7 months for buildings with 20 or more units.

Projects with 10 to 19 units averaged 18.5 months. Five-to-nine-unit buildings took 21.5 months, up from 19.1 months in 2024 and 13.2 months in 2015. The results show that the 2025 improvement was not uniform by size. Most categories shortened modestly, but five-to-nine-unit buildings moved in the opposite direction and took longer than in 2024.

Regional Timelines Remain Uneven

The Northeast posted the longest average permit-to-completion period at 21.9 months. The West followed at 20.6 months, while the South averaged 17.5 months. The Midwest had the shortest timeline at 16.6 months.

Northeast multifamily timelines were longest at 21.9 months in 2025, versus 16.6 months in the Midwest, 17.5 South, and 20.6 West.

Those differences show that the national average masks a wide range of development schedules. Longer multifamily development timelines can therefore look very different depending on project size and region. The spread between the Northeast and Midwest was 5.3 months in 2025, underscoring the regional variation in the survey.

Why It Matters

The growing share of large projects helps explain part of the long-term increase. Buildings with at least 50 units represented 57% of multifamily buildings in 2025, up from 43% in 2009. Larger properties generally require more time to complete, so the market’s shift toward bigger projects has lengthened the overall construction cycle.

The 2025 decline is still meaningful because it came while skilled labor remained constrained. However, completion schedules remain materially longer than they were a decade or more ago. The combination of larger average projects and persistent labor constraints helps explain why modest annual improvement has not returned construction duration to earlier norms.

Related To

RECENT NEWSLETTERS

View All
CRE Daily - No Cap

podcast

No CAP by CRE Daily

No Cap by CRE Daily is a weekly podcast offering an unfiltered look into commercial real estate’s biggest trends and influential figures.

CRE Daily Newsletters

Join 65k+
  • operators
  • developers
  • brokers
  • owners
  • landlords
  • investors
  • lenders

who start their day with CRE Daily.

The latest news and trends in commercial real estate delivered to your inbox. Get smarter about what matters in just 5-minutes or less.