- Data center-adjacent users accounted for 52.8% of tracked large-block industrial leasing in East Bay/Oakland and 30.8% in Salt Lake City from Q3 2024 through Q2 2026.
- A few large deals, including OpenAI in Richmond and MiTAC and Quanta leases in Fremont, Hayward and Newark, make up much of East Bay’s total, said Savills’ Chris Bauers.
- East Bay’s exposure runs through hardware supply, so a slowdown in data center construction would hit industrial demand there, though the effect would take time.
Data center-related tenants drove 52.8% of large-block industrial leasing in East Bay/Oakland, according to a Savills outlook covered by Commercial Property Executive on the data center ripple effect.
Salt Lake City was next at 30.8%. The tracked period ran from the third quarter of 2024 through the second quarter of 2026.
Get Smarter about what matters in CRE
Stay ahead of trends in commercial real estate with CRE Daily – the free newsletter delivering everything you need to start your day in just 5-minutes
A Few Big Deals
Savills Research Manager Chris Bauers cautioned that East Bay has far less large-block leasing than Dallas-Fort Worth, Houston, Phoenix or Atlanta. That means a handful of deals carry the total.
He pointed to OpenAI in Richmond, MiTAC in Fremont and Hayward, and Quanta Manufacturing in Newark. In Union City/Fremont, MiTAC signed 210,795 square feet and Quanta 210,000.
Why the East Bay
Bauers told Commercial Property Executive the region already hosts OpenAI and MiTAC, so expanding nearby is logical. The area’s tech and manufacturing base also supplies the specialized labor these operations need.
The East Bay’s niche is hardware supply, which carries exposure to data center construction slowdowns. Bauers said any industrial impact would take time to show.
Why It Matters
Data center demand is reaching beyond the big hubs. We reported that the data center boom drove 69 million square feet of industrial leasing, and the Savills data shows how concentrated that effect can be in smaller markets.
For landlords, the takeaway is to separate durable demand from a few headline leases.
What’s Next
Watch whether more hardware users follow OpenAI and MiTAC into the East Bay, and whether a slowdown in data center construction shows up in leasing.