- Turner & Townsend found U.S. data center construction costs rose 13% year over year, more than twice the global rate and about three times the ten-year average.
- Power is the biggest bottleneck: 56% of surveyed experts call it a major obstacle, and costs run from $10.51 per watt in Dallas to $15.01 in Silicon Valley.
- Turner & Townsend expects cost growth to ease to 6% to 10% next year because many large projects have already been procured.
U.S. data center construction costs rose 13% over the past year, at over double the pace worldwide, per a Turner & Townsend report cited by CNBC.
That is about three times the ten-year average, as AI demand outran the available powered land and labor.
Get Smarter about what matters in CRE
Stay ahead of trends in commercial real estate with CRE Daily – the free newsletter delivering everything you need to start your day in just 5-minutes
The Report
The firm analyzed over 500 active or finished projects in 62 markets worldwide and polled 400 industry experts.
Cost inflation cooled slightly this year, but not enough to cover the rush for faster delivery.
Speed Costs Money
Paul Barry, who runs the firm’s North America data center work, told CNBC that tighter schedules push contractors and subcontractors to build risk into their bids. That shows up as acceleration allowances, overtime, labor-attraction premiums and higher fees.
Barry said those items, plus the demand spike and supply chain strain, drive the higher costs.
Power and Labor Limits
Of those surveyed worldwide, 56% call power a major obstacle. Just over half say utility hookups take one to two years, and nearly a third say they take longer.
Power costs range from $10.51 a watt in Dallas to $15.01 in Silicon Valley, for a standard 60 MW build. Only about a quarter of respondents say their contractor capacity is sufficient.
Zoom Out
Data centers have been pulling developers away from other asset types for a while. In August 2025 we covered how data center construction was outpacing office development as brokerages pivoted to the sector.
CNBC also cited PwC, which sees global data center capital spending climbing from roughly $800 billion now to $1.8 trillion annually by 2050, with the U.S. capturing nearly half of AI infrastructure investment.
Why It Matters
Higher costs arrive as local resistance grows. Loudoun County, Va., the biggest hub, voted 7-1 to freeze some new approvals for a year, per our report on the Loudoun pause.
Both pressures raise the bar for new projects, favoring developers with power, labor and local approvals already lined up.
What’s Next
Barry told CNBC he expects costs to rise 6% to 10% in the next year, since many big projects are already procured and their cost risk is built into contracts. He said 2026 brought a surge of major new projects.