LA’s $1.2B Graffiti Towers Sage Nears Revival After Bankruptcy

Oceanwide Plaza’s $1.2B LA luxury towers will exit bankruptcy as KPC and Lendlease win approval to revive the project.
Oceanwide Plaza’s $1.2B LA luxury towers will exit bankruptcy as KPC and Lendlease win approval to revive the project.
  • KPC Group and Lendlease have received court approval to acquire and finish Oceanwide Plaza in downtown Los Angeles for $517M plus $800M in completion costs.
  • The 60%-built ‘Graffiti Towers’ stalled in 2018 after its Chinese sponsor lost funding; its high-profile blight and safety issues have dogged LA as it prepares for the 2028 Olympics.
  • This green light may mark a turning point for stalled mega-projects and international investor unwinding in core US urban markets.
Key Takeaways

China’s Megaproject Bust Sets the Stage

Oceanwide Plaza, three unfinished towers beside Crypto.com Arena, became a symbol of stalled global investment in downtown Los Angeles. Bloomberg reported construction stopped in 2018 after Beijing restricted overseas investment by developer China Oceanwide Holdings. The project was about 60% complete.

Years of decay, graffiti, and negative headlines followed before bankruptcy proceedings began in 2024. The abandoned towers attracted taggers and thrill-seekers, raising public safety concerns. City leaders and CRE professionals also worried about downtown’s image before the 2028 Olympics.

The Details

A joint venture between KPC Group and Lendlease Americas will acquire the 1.5M SF project for about $517M. Bloomberg reported the deal combines cash and credit. KPC also plans to invest about $800M to finish the hotel, condo, and retail project.

The acquisition includes $70M in cash and a $400M credit bid. The credit bid covers unpaid construction bills and senior debt claims from Chinese EB-5 investors.

Bankruptcy Judge Deborah Saltzman will enter the order this week. City agencies and creditors dropped their objections after KPC accepted several conditions. These include immediate graffiti removal, permit renewals, and a backup bidder if the deal fails. KPC will also pay additional tax, legal, security, and architectural costs.

Post-Pandemic Urban Reset

Oceanwide Plaza reflects the collapse of cross-border financing for major US developments. Many projects with Chinese backing have stalled or failed during the past five years. Few occupy a more visible location than this site near the convention center and South Park.

Los Angeles now faces pressure to revive a project with global visibility before the 2028 Olympics. The restart could influence other distressed or unfinished CRE projects across the city.

Why It Matters

Oceanwide Plaza’s revival reaches beyond one investment or one skyline. Downtown Los Angeles still struggles to recover after the pandemic. Hospitality, residential, and retail vacancies remain elevated. CBRE reported downtown office vacancy exceeded 25% in 2026, while retail availability also stayed high.

Completing the project will not solve those challenges alone. However, it can reassure investors and city leaders that major US developments remain attractive. Improving lending activity among regional banks could also expand financing options for similar redevelopment projects. The restart also pressures other cities and creditors to pursue practical solutions for stalled projects.

Mayor Karen Bass said the project will restore confidence and unlock South Park’s economic potential. Meanwhile, KPC continues expanding across Southern California. Its projects include a 300-room Inglewood hotel and a 17,000-home Coachella community. Lendlease also brings experienced oversight despite exiting US contracting.

The cleanup will immediately remove graffiti and strengthen site security. Those improvements will show civic and business leaders that downtown blight can be reversed. Delivering before the 2028 Olympics remains ambitious. Still, the restart offers an early test for future large-scale urban CRE recoveries.

What’s Next

KPC Group and Lendlease plan to begin with graffiti removal and site cleanup. Next, they must renew permits and coordinate with city planners. If everything stays on schedule, major construction could resume by late 2026. The partners hope to complete key hotel and residential components before the 2028 Olympics.

The broader Los Angeles CRE market will closely watch the project. Investors, lenders, and city officials want to see how this workout performs. They will also evaluate the hybrid cash-and-credit structure under court supervision. Debtors’ attorney Sharon Weiss said, “That is the strongest possible evidence of feasibility,” highlighting expectations for the project’s next phase.

RECENT NEWSLETTERS

View All
CRE Daily - No Cap

podcast

No CAP by CRE Daily

No Cap by CRE Daily is a weekly podcast offering an unfiltered look into commercial real estate’s biggest trends and influential figures.

CRE Daily Newsletters

Join 65k+
  • operators
  • developers
  • brokers
  • owners
  • landlords
  • investors
  • lenders

who start their day with CRE Daily.

The latest news and trends in commercial real estate delivered to your inbox. Get smarter about what matters in just 5-minutes or less.