- SpaceX unveiled $74B in data center campuses: a $50B site in Cochise County, Arizona, and a $24B, 444-acre development near Starbase, Texas.
- Texas would run on a gas plant SpaceX owns, while Arizona leans partly on local cooperative power and cooling designed to avoid groundwater use.
- The timing matters: both states just elected leaders pushing tighter data center rules, so even self-powered mega-campuses now carry more political and permitting risk.
SpaceX picked a tense moment to unveil $74B in data center campuses, according to Bisnow.
An Arizona campus in Cochise County is priced at $50B, and a 444-acre Texas project near Starbase at $24B, Bisnow reported.
Get Smarter About What Matters in Texas
Subscribe to our free newsletter covering the biggest commercial real estate stories across Texas — delivered in just 5 minutes.
Two Power Strategies
The Texas campus would rely on a gas-fired power plant built and owned by SpaceX, Bisnow reported.
Arizona would take a different approach. The project would rely at least partly on local electric co-ops. SpaceX also says it will tap renewable capacity already on the grid and use cooling systems that avoid groundwater.
From Rockets to Racks
Musk now pitches SpaceX as a computing supplier. The company would provide capacity for Grok and outside cloud giants. This shift follows February’s $1.25T all-stock xAI deal, according to Bisnow.
Today, SpaceX’s computing capacity sits almost entirely near Memphis, at the Colossus I and Colossus 2 campuses. Advocacy groups allege that generators operated without federal permits. The Justice Department has asked a judge to dismiss lawsuits filed by the NAACP and Southern Environmental Law Center on national security grounds.
The Political Backdrop
The announcement came a little over a week after elections that went badly for data center boosters. Democrat Gina Hinojosa defeated Gov. Greg Abbott in Texas. Stricter data center policy was a centerpiece of her campaign.
Musk reportedly spent about $180M backing Republicans in Texas, including $5M for Abbott. After the elections, he posted on X that data centers in space look “pretty appealing right now.”
Arizona Faces Pushback Too
Democrats won both chambers of the Arizona legislature and kept the governor’s office. As a result, some legislators are openly discussing a pause on new projects. Gov. Katie Hobbs, however, opposes a blanket moratorium.
Zoom Out
The Texas half of the plan isn’t new. We covered the Starbase plan on Nov. 10. A city hearing notice showed $24B for the first phase and a Dec. 9 commissioners meeting on a tax abatement.
Why It Matters
Self-supplied power can sidestep grid queues, but it doesn’t avoid political risks. Our earlier reporting on Democratic midterm wins found that roughly half of proposed U.S. data center additions could face heightened scrutiny.
A $74B commitment shows that capital isn’t waiting for policy clarity. Lenders and developers will watch whether approvals keep pace.
What’s Next
Starbase commissioners will consider the abatement on Dec. 9. Hinojosa takes office Jan. 19. Her campaign promises will then face the realities of the permitting process.